Mission ISS-5A.1
Mission Description:
The primary objective of STS-102 is ISS Assembly Flight 5A.1 This mission will deliver logistics and experiments to ISS using the Leonardo Multi-Purpose Logistics Module (MPLM). This mission will also deliver the Expedition 2 crew (Yuri Usachev, James Voss and Susan Helms) to the ISS and will return the Expedition 1 crew (Bill Shepherd, Sergei Krikalev and Yuri Gidzenko) to Earth.
Cargo Manifest. Note: [numbers] = ISS SE (Subelement) numbers.
Ascent Cargo
- MPLM-1 Module Core [470],
- 6 U.S. Lab System Racks [6,7,9,11,12,28],
- 3 Resupply Stowage Racks [150,151,152],
- 4 Resupply Stowage Platforms [180, 181, 182, 188]
- ISPR ICC [105R2],
- U.S. Lab Cradle Assembly [248], Early Ammonia Servicer [263], Pump Flow Control Subassembly [267], U.S. Lab PDGF Rigid Umbilical [26],External Stowage Platform [107],
- SILL ISS Content [975D]
- Middeck ISS Content [800AL, 801G, 802, 803C], Shuttle Integration H/W [850AL]
|
Descent Cargo
- MPLM-1 Module Core [470],
- 3 Resupply Stowage Racks [150,151,152],
- 4 Resupply Stowage Platforms [180, 181, 182, 188]
- ICC [105R2]
|
EVA Activity
30 November 2000: XA/EVA Project Office Weekly Activity Report
Addition of 3rd EVA to 5A.1 As a result of detailed evaluations of the 5A.1 EVA NBL runs it was determined that the Pump Flow Control System transfer and the Rigid Umbilical connection task could not be completed in the allotted times for EVA 1 and EVA 2. The proposed recommendation, which was approved by the 11/15/00 EVA CCB and PRCB, was to add a third, 14.7psi EVA with a 4:30 duration. The decision was also made to protect consumables for a 4th, unscheduled 14.7psi EVA.
|
EVA TASKS TO BE PERFORMED
|
CREW TO PERFORM EVA |
AIRLOCK USED |
SPACESUIT USED |
ASSEMBLY or MAINTENANCE |
Flight 5A.1 - EVA 1
Disconnect/stow PMA3-Node1 Umbilicals. (16)
Remove port Node 1 ECOMM antenna.
Install Lab Cradle Assembly onto Lab.
Rigid Umbilical install onto Lab.
Move PMA3 to Node 1 port CBM. (RMS)
Dock MPLM onto Node 1 nadir CBM. (RMS)
|
STS |
Shuttle |
EMU |
Assembly |
Flight 5A.1 - EVA 2
Early Ammonia Servicer remove from SLP, install onto P6 trunnion.
Connect Z1 EAS heaterlines.
External Stowage Platform remove and install on Lab trunnion.
Connect Rigid Umbilical cables.
Install PFCS onto ESP.
Route PFCS heaterlines.
Activate CIDs.
RMS undock MPLM from Node 1.
|
STS |
Shuttle |
EMU |
Assembly |
Operations Documents
|