Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads. If you are a member of the media and would like further information, visit: http://www.nasa.gov/centers/kennedy/news/index.html
Mission: STS-122 - 24th International Space Station Flight - Columbus laboratory
Vehicle: Atlantis (OV-104)
Location: Launch Pad 39A
Launch Date: Feb. 7
Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin, Walheim
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Launch Pad 39A
- Launch countdown preparations continue.
- Call to stations is scheduled for Feb. 4 at 4:30 p.m.
- Payload bay door radiator retract hose issue fix under way
- Hose located on starboard aft
- X-rays show hose is in good condition and no leaks were detected
- Engineers designed tool to guide flex hose back into storage box
- Technician performing work tested the method Thursday with success
- Payload bay doors scheduled to close using method on Sunday
- Orbiter aft closeout was completed Thursday
- Leak check was performed at the purge port of fuel cell No. 2, where no leaks were detected
- Flight crew stow operations were conducted
Mission: STS-123 - 25th International Space Station Flight - Kibo, Dextre
Vehicle: Endeavour (OV-105)
Location: Orbiter Processing Facility Bay 2
Launch Date: Targeting March 11
Launch Pad: 39A
Crew: Gorie, Johnson, Linnehan, Doi, Behnken, Foreman, Reisman
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Orbiter Processing Facility Bay No. 2
- Final roll preparations and aft closeout for rollover under way
- Orbiter/external tank mate planned for Feb. 11
- Thermal protection system processing and closeout in process
- Aft compartment platforms and inspections continue
Vehicle Assembly Building High Bay No. 1
- Engine cutoff sensor system electrical feed-through connector work is in work
- External tank is mated with the solid rocket boosters
Mission: STS-124 - 26th International Space Station Flight - Kibo
Pressurized Module, Japanese Remote Manipulator System
Vehicle: Discovery (OV-103)
Location: Orbiter Processing Facility Bay 3
Launch Date: Targeting April 24
Launch Pad: 39A
Crew: Kelly, Ham, Nyberg, Garan, Fossum, Hoshide, Chamitoff
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Orbiter Processing Facility Bay No. 3
- Two reinforced carbon-carbon panels have been installed for flight and two more are in the process of being installed
- Ku-band antenna was deployed Wednesday
- Drag chute flight door installation completed Jan. 28
Vehicle Assembly Building High Bay No. 3
- Solid rocket booster stacking begins Feb. 4
- Decorate your home with nautical decor
- Dieses Portal stellt Ihnen die besten online Casino Bonus und Pokerräume im Internet vor.
- Play free bingo games and black out bingo.
- 220Marketing specializes in providing mortgage marketing for mortgage companies and managers.
- Take your time to tour our site and check out all the fun games we operate. In addition to the 20 online bingo rooms we operate, we also have online keno.
- TV Stands