GAO: Area I and Orion Project Risk and Key Indicators to Measure Progress

 
STATUS REPORT
Date Released: Thursday, April 3, 2008
Source: Government Accountability Office


image

Full Report

What GAO Found

NASA is currently working toward preliminary design reviews for the Ares I and Orion vehicles. While this is a phase for discovery and risk reduction, there are considerable unknowns as to whether NASA's plans for these vehicles can be executed within schedule goals and what these efforts will ultimately cost. This is primarily because NASA is still in the process of defining many performance requirements. Such uncertainties could affect the mass, loads, and weight requirements for the vehicles. NASA is aiming to complete this process in 2008, but it will be challenged to do so given the level of knowledge that still needs to be attained. The challenges NASA is facing pose risks to the successful outcome of the projects. For example:

  • Both vehicles have a history of weight issues;
  • Excessive vibration during launch threatens system design;
  • Uncertainty about how flight characteristics will be impacted by a fifth segment added to the Ares I launch vehicle;
  • Ares I upper stage essentially requires development of a new engine;
  • No industry capability currently exists for producing the kind of heat shields that the Orion will need for protecting the crew exploration vehicle when it reenters Earth's atmosphere; and
  • Existing test facilities are insufficient for testing Ares I's new engine, for replicating the engine's vibration and acoustic environment, and for testing the thermal protection system for the Orion vehicle.

All these unknowns, as well as others, leave NASA in the position of being unable to provide firm cost estimates for the projects at this point. Meanwhile, tight deadlines are putting additional pressure on both the Ares I and Orion projects. Future requirements changes raise risks that both projects could experience cost and schedule problems.

GAO's past work on space systems acquisition and the practices of leading developers identifies best practices that can provide decision makers with insight into the progress of development at key junctures, facilitate Congressional oversight, and support informed decision making. This work has also identified common red flags throughout development, which decision makers need to keep in mind when assessing the projects. They include:

Key indicators: Weight growth is often among the highest drivers of cost growth. Unanticipated software complexity, often indicated by increases in the number of lines of code, can portend cost and schedule growth.

Key junctures: The preliminary design review, critical design review, and production review are key junctures that involve numerous steps and help focus the agency on realistic accomplishments within reachable goals. A disciplined approach aligned with key indicators can provide the knowledge needed to make informed investment decisions at each review.

Why GAO Did This Study

The National Aeronautics and Space Administration (NASA) is in the midst of two new development efforts as part of the Constellation Program--the Ares I Crew Launch Vehicle and the Orion Crew Exploration Vehicle. These projects are critical to the success of the overall program, which will return humans to spaceflight after Space Shuttle retirement in 2010. To reduce the gap in human spaceflight, NASA plans to launch Ares I and Orion in 2015--5 years after the Shuttle's retirement.

GAO has issued a number of reports and testimonies that touch on various aspects of NASA's Constellation Program, particularly the development efforts underway for the Orion and Ares I projects. These reports and testimonies have questioned the affordability and overall acquisition strategy for each project. NASA has revised the Orion acquisition strategy and delayed the Ares I preliminary design review based on GAO's recommendations in these reports. In addition, GAO continues to monitor these projects on an ongoing basis at the request of members of Congress. Based on this work, GAO was asked to testify on the types of challenges that NASA faces in developing the Ares I and Orion vehicles and identify the key indicators that decision makers could use to assess risks associated with common trouble spots in development. The information in this testimony is based on work completed in accordance with generally accepted government auditing standards.


Share and Enjoy: These icons link to social bookmarking sites where readers can share and discover new web pages.
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Reddit
  • Slashdot
  • StumbleUpon
  • Technorati
  • TwitThis
  • Fark
  • Google
  • Live
  • YahooMyWeb

Mercury - Venus - The Moon - Mars - Jupiter - Saturn - Pluto

RADWIN empowers service providers so they can deliver high speed Wireless broadband Access services.

Find hose reels and watering systems

Quality leather chairs in a variety of styles.


 


News from Commercial Space Watch

- Recovery Act: Water Management in California: Cyber Infrastructure for Irrigation Optimization

- Former Shuttle Astronaut-Astronomer, Sam Durrance, Joins the CSF Suborbital Researchers Group

- Satellite-Based Earth Observation Market Entering Phase of Impressive Growth

- NASA and Lighting Science Sign Agreement to Develop Lighting for Space Exploration

- Sky No Longer the Limit for Digital Magazines

- NASA Develops Algae Bioreactor as a Sustainable Energy Source

- Aerojet Engines Support Space Shuttle Atlantis' Re-stocking Mission to International Space Station

- Suborbital Applications Researchers Group Meets in Washington

- NewSpace Is Under Attack

- Pratt & Whitney Rocketdyne Successfully Tests Thruster for Unmanned Lunar Lander

- bacus Technology Corporation Awarded NASA Kennedy Space Center Small Business Prime Contractor of the Year - 2009

- NASA ARC Memo; Procurement Sensitivity of the Competition of Aeronautics and Exploration Mission Modeling and Simulation Request for Proposal NNA09274979R

- Lockheed Martin Tests Carbon Nanotube-Based Memory Devices on NASA Shuttle Mission

- Leonid Meteor Shower to Perform Late Tonight

- Sri Lanka signs agreement with SSTL for space capability

- Decorate your home with nautical decor

- Dieses Portal stellt Ihnen die besten online Casino Bonus und Pokerräume im Internet vor.

- Play free bingo games and black out bingo.

- 220Marketing specializes in providing mortgage marketing for mortgage companies and managers.

- Take your time to tour our site and check out all the fun games we operate. In addition to the 20 online bingo rooms we operate, we also have online keno.

- TV Stands

advertisment

Learning About Telescopes

Learn about Telescopes

Recent Status Reports

Recovery Act: Water Management in California: Cyber Infrastructure for Irrigation Optimization

NASA MODIS Image of the Day: November 21, 2009 - Dust over Afghanistan

NASA Hubble Space Telescope Daily Report #4976

NASA Hubble Space Telescope Daily Report #4975

NASA Hubble Space Telescope Daily Report #4974

Porters Tahoe is the premier online dealer for Skis and Burton Snowboards, visit PortersTahoe.com!

Tax Free Cigarettes

Looking for TV Trays. Find a wide selection

Bingo world tour - The most comprehensive guide to Play Online Bingo Games

Find a number of writing desks for sale

the best online casinos guide on the internet offering higher payouts than any land based casino.

Paradise Style Group - wedding and special occasion dresses.

Design and Sell Merchandise Online for Free